B144 - Collateral Warranty Agreement (Subcontractor)

 

Collateral Warranty Agreement (Subcontractor)

Collateral Warranty Agreement (Subcontractor)

For use where a sub-contractor enters into a direct agreement with a purchaser, tenant or funder of a development.

This four page document contains 9 clauses covering

  • definitions
  • warranty
  • deleterious materials
  • copyright
  • indemnity insurance
  • assignment & third party rights
  • notices
  • law & jurisdiction
  • step-in rights

The contract is accompanied by Explanatory Notes that explain the background and purpose of collateral warranties as well as dealing with individual clauses in the document.

You need this document if you are a subcontractor entering into a direct agreement with a purchaser, tenant or funder of a development.

[English law edition]


What's in it? - See detailed Explanatory Notes below

ShareThis

Buy Collateral Warranty Agreement (Subcontractor) online

£30.00 + VAT

In Stock

Your ContractStore purchase will be available for online download from the 'My Account' area immediately after you have paid.

 


Add to favoritesClick here to add this page to your favourites/bookmark.

You will find this contract in:

Building and Construction
Full Catalogue

 

 

 

 


 

What's in it?

Whilst for obvious reasons we can't show you the actual item before you purchase it, we can do the next best thing. We show you the explanatory notes that go with each contract and, in the case of books and forms, a brief summary. These will give you a good idea of the content of the document before you buy it. 

 

Explanatory Notes


INTRODUCTION

A Collateral Warranty is an agreement between a consultant or contractor involved in the design and/or construction of a development and a third party, the beneficiary, who acquires an interest in that development.  The beneficiary may be a purchaser or tenant or a bank or other company providing the finance for the development. 

The purpose of a Collateral Warranty agreement is to create a contractual link between the beneficiary and a consultant or contractor involved in its construction.  Under the English law of negligence, as it has developed over the years, the end-user of property who suffers economic loss because of defects that are due to negligence on the part of the builder or designer, is unlikely to be able to recover any damages if he sues that builder or designer.  However, by having a collateral agreement between the designer or builder and the end-user, this problem is overcome - the beneficiary can sue the designer or builder under the collateral agreement on the grounds that there has been a breach of contract.

In this case, the warranty agreement is being given by a subcontractor of the main contractor for the development.  As much of the work on a development is subcontracted by the developer's main contractor, it is common for the most important subcontractors, in particular those with a design responsibility, to be asked to provide a collateral warranty in favour of a third party purchaser etc.  It is also quite common for the developer himself to require a warranty from those subcontractors: the existence of the warranty agreement gives the developer a right of recourse directly against the subcontractor for negligence as well as the opportunity to step into the shoes of the main contractor and take over the subcontract, in the event of the main contractor's insolvency

Collateral Warranties are unlike most contracts, in that the two parties to the collateral agreement do not have any real commercial relationship.  Indeed, it is unlikely that they will ever speak to each other.  The beneficiary, under his agreement with the developer, is likely to have a requirement for collateral warranties.  This requirement is then imposed on the consultant or contractor in his contract with the developer.  And the contractor will pass down the obligation to those of his subcontractors who may be required to provide a collateral warranty.
 
The precise terms of the Collateral Warranty agreement are usually negotiated amongst the lawyers for the various parties.  Over time the wording of warranty agreements has been developed and our form is in line with current developments in the English legal market.

Consultants and contractors maintain professional indemnity insurance to cover their potential liability in negligence.  It is therefore usual for a consultant or contractor, when presented with a Collateral Warranty, to refer that document to his insurance brokers.   It is important for all parties that the wording of the Warranty is acceptable to the insurers so that, if a claim does arise, the insurers will be there to meet the claim - up to the insured limit which sometimes, but by no means always, is also the limit of the contractor/consultant’s liability under the Collateral Warranty agreement. 

One further general point:  a Collateral Warranty agreement is usually executed as a “deed”.  Under English law, a document, which is executed as a deed, differs from an ordinary agreement in two respects.   Firstly, the limitation period - i.e. the time after a breach of contract has occurred within which one party can sue another - is 12 years, as opposed to 6 years for an agreement which is executed “under hand”.  Secondly, whereas under English law consideration is needed for a contract to be effective, that is not the case with a deed. 

There is more information on deeds in our free note at this address: http://www.contractstore.com/signing_contracts

SPECIFIC CLAUSES

Turning to the specific terms of the agreement:

DATE.  This will be the date upon which it is executed by all the parties.

PARTIES.  The subcontractor who gives the warranty - sometimes known as the warrantor - will be one party. The "Beneficiary" will be either the employer under the main contract - i.e. the developer - or a purchaser, funder or tenant of the development.  In our document we have also provided for the main contractor to be a party but this is only required if clause 9 applies.   See our comments under clause 9 below.

1. DEFINITIONS

 This clause will need to be completed with various details, including a brief description of the development, and of the subcontract works.   The “Subcontract” is the contract to which this Collateral Warranty agreement is collateral and the date should be specified.   Since the obligations of the subcontractor under this agreement parallel his obligations under the subcontract, the beneficiary should always ask to see a copy of the contract and it is not unknown for a copy to be attached to a Collateral Warranty agreement.  If, for example, there are restrictions on the subcontractor’s liability in the subcontract, that might affect the rights of the beneficiary under the Collateral Warranty. 

 “Insured Sum” and “Insurance Period” relate to the professional indemnity insurance being maintained by the subcontractor - see clause 4.   The insurance period will usually be 12 years from the date of completion - see the comments above concerning a deed.

2. WARRANTY

 In this clause, the subcontractor gives warranties to the beneficiary that it has exercised and will continue to exercise reasonable skill and care in its obligations to the contractor under the subcontract.

 Clause 2.1 is broken into 3 parts, Clause 2.1.1 imposes a duty of care on the contractor.  Clause 2.1.2 contains a warranty with respect to design.  Clause 2.1.3 has a specific warranty with regard to the obligations under the subcontract.

 Clause 2.2 makes it clear that the subcontractor's liability under this agreement is no greater than that under the subcontract.

3. DELETERIOUS MATERIALS

 It is usual to have a clause separate from the general warranty obligations, under which a contractor gives a warranty that it will not specify or use materials, which are generally known to be deleterious to health and safety. 

4. COPYRIGHT

 It is usual for a beneficiary under a Collateral Warranty agreement to have a right to use designs and other documents prepared by the subcontractor but only in connection with the building for which those design documents are prepared.  Copyright is retained by the subcontractor.

 Under clause 4.3, the beneficiary has to pay for copies of any drawings and documents, which it may request.

5. INDEMNITY INSURANCE

 This clause imposes on the subcontractor an obligation to maintain professional indemnity insurance during the construction period and until the risk of legal proceedings against him has passed - i.e. for the limitation period which is specified in clause 1.  This is usually a period which commences with the subcontract and ends 12 years after completion of the main contract.  (In this connection, the terminology used in the main contract – “Practical Completion” or “Taking Over” should be used in the Collateral Warranty agreement to avoid any inconsistency.)

 If the subcontract is not itself executed as a deed, the limitation period under that contract will not exceed 6 years.  In those circumstances, the same period should apply in the Collateral Warranty agreement - otherwise the subcontractor would have a greater liability to the beneficiary under this document than he would to the contractor under the principal contract.

 Clause 5.3 contemplates the possibility of professional indemnity insurance ceasing to be available at commercially acceptable rates.  It does not say what will happen except that the parties will meet to try to resolve the matter amongst themselves.

 N.B. Not every subcontractor maintains professional liability insurance and in that case the clause may have to be omitted.  Alternatively, if the subcontractor is a supplier of plant or equipment, it may have product liability insurance, in which case the clause can be adapted to refer to product liability insurance instead of professional indemnity insurance.

6. ASSIGNMENT & THIRD PARTY RIGHTS

 Although a modest little clause, the wording of an assignment clause in a Collateral Warranty agreement can generate a lot of argument.  The main reason for this is because professional indemnity insurers like to limit their risks by imposing restrictions in their policies.  The standard practice nowadays is to allow the benefit of a Collateral Warranty agreement to be passed on twice by the beneficiary.  Usually this will occur when the beneficiary is an owner or tenant and wants to sell his interest.

 In clause 6.1 the words "not to be unreasonably withheld" may be resisted by insurers - hence they are optional.

 Clause 6.3 states that the Contracts (Rights of Third Parties) Act 1999 does not apply.  There is a certain irony here: that Act was introduced to enable a third party in certain circumstances to have the benefit of a contract made between two other parties in which the third party has an interest - i.e. the end-user of a development such as the one contemplated here.  Sadly, English solicitors generally take the view that it is better to continue with the use of Collateral Warranty agreements rather than take advantage of this new legislation, which could dispense with the need for those agreements!   Having said this, where a collateral warranty agreement is entered into, there is little point in having undefined third parties getting any benefit.

7. NOTICES

 This is a standard provision and needs no comment.

8. LAW & JURISDICTION

 We have specified that English law governs this agreement and that the English courts will have jurisdiction.  Collateral Warranties, thanks to the spread of English lawyers around the globe, are being used in other jurisdictions.  However, if some law other than English law is to apply, care should be taken since the form of Collateral Warranty which we have provided is designed for use in England and may not be appropriate elsewhere.

9. STEP-IN RIGHTS

 This clause, as indicated, is only appropriate when the beneficiary is the developer.  In those circumstances, if the main contractor becomes insolvent or if the subcontractor wants to terminate his contract, the developer may want to take over the subcontract from the contractor so that the subcontract works can continue without interruption.  Clause 9 has the effect of varying the terms of the subcontract by requiring the subcontractor to give notice to the contractor before he terminates the subcontract.  The beneficiary then has the right to take over the contractor's role under the subcontract and an obligation, under those circumstances to pay the subcontractor any money that is outstanding. 

 Consequently this clause has a potential benefit for the subcontractor: the developer may rescue it if the main contractor becomes bankrupt.  As will be seen, there are strict time limits contained in the clause and the beneficiary does not have any obligation to step in - only the right to do so. 

 As the effect of clause 9 is to vary the subcontract it is important that, when the collateral warranty contains such a clause, the contractor should be a party to that document in order for the clause to be effective.

Back to top

 

 

 

 

 

Important Notice
This notice applies to all materials and information available on this website.

The contents of this site are protected by copyright. They may not be reproduced, distributed or published in any way without the consent of The ContractStore Ltd.

All information and materials on this site are provided on an 'as is' basis and are not intended in any way to be comprehensive. Any reader making use of this site does so at his/her own risk and readers are advised to take independent professional advice before acting on any information or materials found here. The ContractStore Ltd accepts no responsibility and gives no representations or warranties, express or implied, that any of the information and materials on this site are complete, accurate or free from errors or omissions.

Registered office: Acre House, 11/15 William Road, London NW1 3EW, United Kingdom
©ContractStore Ltd, 2012. All rights reserved.

Contact us | About us | CookiesCopyright notice | Terms and Conditions

 We use cookies to provide visitors with a good user experience. New regulations mean we need your consent for this use. For more information click here